In the main Brize Norton Base Hanger, the Air Force had major problems maintaining consistent pressure inside the pipe work system.

Motivair was called in to provide a solution and recommended that the 600 metres of pipe work be formed into a ring main with larger bore 80mm Opus 9 HBS Aluminium Extrusion piping.

The pipe work was installed in just three weeks. This was carefully coordinated with the RAF to give them minimum down time in the six service bays. Problem solved.